Workshop Update 19th April

19th April, 2017

  BR Standard Class 4MT 2-6-4 T  No 80097   The boiler was not ready for the planned hydraulic test on the 13th February although work has been continuing. It was reported that the flue tube holes were all out of round and this greatly…

Full story...

Workshop Update 9th February 2017

9th March, 2017

    Standard 4 mt Loco 80097   Further delays have occurred with the boiler work and it was not ready for a planned hydraulic test on the 13th February. A revised date has not yet been set. The delay was caused by additional work…

Full story...

Workshop Update 9th February 2017

Boiler Update

18th December, 2016

On Wednesday 14th December the Directors of the Bury Steam Locomotive group received an email from Adam Dalgleish Engineering. He has informed us he is aiming for the hydraulic test w/c 13/02/2017.  This date is dependent on the if the boiler inspector finds any additonal…

Full story...

Update

27th November, 2016

We understand that things have been quiet recenty with regard to the progress of the boiler. The Directors would like to inform you that work is slowly progressing and discussions are currently taking place. We will update you as soon as possible and your ongoing support…

Full story...

Workshop Update 16th November

16th November, 2016

  Standard 4 mt Loco 80097   The boiler is still at Dalgleish Engineering where they are having ongoing problems with the longtitudinal stays.  Nigel has made a replacement logtitudinal stay and delivered it to Dalgleish.   Nigel has also started machining the injector bodies.…

Full story...

Workshop Update 11th August

11th August, 2016

  Standard 4 mt   80097   We are still waiting for the boiler to be returned. A final action plan has now been prepared with Dalgleish Engineering and we are now expecting the boiler to be returned with a steam test ticket in mid October.…

Full story...

Workshop Update 11th August

Workshop Update 22nd June

22nd June, 2016

  On 80097, the problem with the longtitudinal stays has now been resolved and work is progressing on the boiler. The forecast from the Dalgleish company is still for a July return.   Engineering work has now been completed on the High Fit wagon and…

Full story...

Workshop Update 10th May

10th May, 2016

  A small amount of work continues on the loco whilst we wait for the return of the boiler.   The injector bodies have been taken to a local engineering firm for final machining.   The boiler company, Dalgliesh Engineering have had a problem with…

Full story...

Workshop Update 10th May

AGM For Shareholders - Thursday 5th May

28th April, 2016

Dear Shareholder, The AGM reference above will be held in the Bury Transport Museum Education Suite on Thursday 5th May 2015 commencing 19: 30 hours. As in previous year’s, copies of the accounts will be made available to attendees.       If you have any items which…

Full story...

Workshop Update 7th March

7th March, 2016

  Bob has completed the locker fittings in the cab. He and Stuart have fitted the roof securing bracket in the cab.   Dave and Bob have been preparing coupling links for the loco.   Harry has now completed checking all the assemblies bolted onto…

Full story...

Workshop Update 7th March